Wednesday, November 25, 2026
  • About
  • Advertise
  • Privacy Policy
  • Cookie Policy
  • Contact
  • Subscribe
  • E-edition
  • Login
  • Register
  • Home
  • News
  • Economy
  • E-Edition
  • Companies & Markets
  • In Business With
  • Lifestyle
    • Motoring
  • Sports
    Defining Week Awaits Botswana’s National Teams

    Defining Week Awaits Botswana’s National Teams

    Botswana Bets on Horse Racing for Jobs and Economic Growth

    Botswana Bets on Horse Racing for Jobs and Economic Growth

    Maotoanong remembered for laughter, loyalty and Botswana pride

    Maotoanong remembered for laughter, loyalty and Botswana pride

    Orebonye seeks fresh start at Hassania Agadir

    Orebonye seeks fresh start at Hassania Agadir

    SCHOOL SPORT NEEDS MORE THAN A RETURN TO THE FIELD

    SCHOOL SPORT NEEDS MORE THAN A RETURN TO THE FIELD

    TONOTA FC TAKES BOTSWANA FOOTBALL INTO NEW TERRITORY

    TONOTA FC TAKES BOTSWANA FOOTBALL INTO NEW TERRITORY

  • Subscribe
No Result
View All Result
  • Home
  • News
  • Economy
  • E-Edition
  • Companies & Markets
  • In Business With
  • Lifestyle
    • Motoring
  • Sports
    Defining Week Awaits Botswana’s National Teams

    Defining Week Awaits Botswana’s National Teams

    Botswana Bets on Horse Racing for Jobs and Economic Growth

    Botswana Bets on Horse Racing for Jobs and Economic Growth

    Maotoanong remembered for laughter, loyalty and Botswana pride

    Maotoanong remembered for laughter, loyalty and Botswana pride

    Orebonye seeks fresh start at Hassania Agadir

    Orebonye seeks fresh start at Hassania Agadir

    SCHOOL SPORT NEEDS MORE THAN A RETURN TO THE FIELD

    SCHOOL SPORT NEEDS MORE THAN A RETURN TO THE FIELD

    TONOTA FC TAKES BOTSWANA FOOTBALL INTO NEW TERRITORY

    TONOTA FC TAKES BOTSWANA FOOTBALL INTO NEW TERRITORY

  • Subscribe
No Result
View All Result
The Business Weekly & Review
No Result
View All Result
Home News

P36.3bn Unspent as Development Budget Execution Falters

• Projects enter the budget before the necessary preparation – Finance Ministry • Project feasibility and project financing are often confused • IMF identified weaknesses in project selection and appraisal processes • Government continues to reviewing projects as fiscal realities and priorities evolve

mm by Baboloki Meekwane
November 25, 2026
in News
Reading Time: 7 mins read
0
Francistown draws inspiration from Durban, Cape Town
Share on FacebookShare on Twitter

Botswana has allocated P230.7 billion to development expenditure over the past 14 years but spent only P194.4 billion, leaving P36.3 billion unspent and exposing persistent weaknesses in project preparation and execution.

According to the 2027/28 Budget Strategy Paper, development spending has fallen below budget in 11 of the past 14 financial years, with the problem becoming significantly worse over the last two years.

Between 2012/13 and 2025/26, Government achieved an overall development budget execution rate of 84.3 percent.

However, recent performance has deteriorated sharply.

Government underspent its development budget by 38.5 percent in 2024/25 and by 29.3 percent in 2025/26.

The combined shortfall of P18.2 billion over those two years accounts for roughly half of the cumulative P36.3 billion underspent during the entire 14-year period.

In 2025/26 alone, development expenditure amounted to P16.16 billion against a revised budget of P22.85 billion, leaving P6.69 billion unspent.

This represented the largest component of the P10.6 billion total expenditure underspending recorded during the year, accounting for 63.4 percent of the shortfall.

The figures suggest that capital projects have borne a disproportionate share of recent spending adjustments.

Overall government expenditure declined by P2.3 billion in 2025/26, with development expenditure accounting for P2.1 billion of that reduction.

Meanwhile, recurrent expenditure remained elevated, with personnel emoluments and pensions absorbing 55.8 percent of government revenue.

The pressure on development spending comes at a time when government has less room to absorb revenue shocks.

The Budget Strategy Paper notes that recurrent expenditure reached P70.1 billion in 2025/26, exceeding total revenue by approximately P649 million.

As a result, fewer resources remain available for infrastructure and other productive investments, particularly as mineral and customs revenues remain vulnerable to external economic conditions.

 

Projects Enter the Budget Before They Are Ready

 

Speaking recently at the Bank Gaborone Insights & Impact Roundtable, Senior Policy Advisor at the Ministry of Finance Naledi Madala attributed part of the problem to projects entering the budget before the necessary preparation, feasibility studies and bankability assessments have been completed.

“This has been happening for many years. We are returning such a significant part of the development budget,” she said.

“It is simply because we put something there that is nowhere ready to be executed.”

“Government ministries continue to return unspent development funds,” she added.

Madala said government must become more deliberate in selecting projects for inclusion in Budget Speeches, particularly as Botswana seeks to demonstrate fiscal discipline to international credit rating agencies.

“We are very much aware that this Budget Speech will need to send a strong message to the credit rating agencies. We need to be absolutely sure that what we are putting on the Budget Speech is what is ready,” she said.

The Ministry’s own assessment reflects this concern.

The Budget Strategy Paper identifies procurement and contracting delays, inadequate project readiness, limited implementation capacity and project-specific challenges as key factors behind weak development expenditure.

Madala said the Botswana Economic Transformation Programme (BETP), around 40 percent of whose projects are major public-sector initiatives, is expected to help address these weaknesses.

She said the programme will focus on strengthening project bankability and feasibility, moving government away from a long wishlist of projects towards an executable investment pipeline.

Government must, she argued, become more realistic about what it can and cannot deliver.

 

Feasibility Is Not Bankability

 

Economist Keith Jefferis, who also spoke at the roundtable, said project feasibility and project financing are often confused.

“A project is not a project being executed until it is funded, till there is a financing plan, whether public, private or a combination,” he said.

According to Jefferis, feasibility studies demonstrate whether projects are technically, economically and financially viable, but they do not automatically secure funding.

For public projects lacking commercial viability, government must determine how much funding it is willing to contribute and how the project will be financed.

For projects targeting private investment, feasibility studies must also establish whether a credible investment and financing structure exists.

This challenge is particularly important for major infrastructure projects that exceed the capacity of the national budget and require partnerships with private investors or foreign governments.

Jefferis cited projects such as the proposed Trans-Kalahari Railway as examples.

The International Monetary Fund’s assessment of Botswana’s public investment management system, published in December 2025, raised similar concerns.

The IMF identified weaknesses in project selection and appraisal processes, noting that project selection criteria were often unclear and appraisal methodologies were sometimes inconsistent.

It also found limited use of cost-benefit analysis and other investment-evaluation tools.

According to the IMF, projects were sometimes initiated without sufficient feasibility studies or risk assessments.

The institution further noted a disconnect between national development planning and budget allocations, as well as weak coordination between ministries and implementing agencies.

These shortcomings can leave projects in government budgets without the institutional arrangements required for implementation.

 

The A1 Highway Illustrates the Challenge

 

Jefferis expects government to continue reviewing, amending and, in some cases, dropping projects as fiscal realities and priorities evolve.

“I think we will continue to see projects being dropped or amended,” he said.

He pointed to differences between the 2025 and 2026 State of the Nation Addresses, particularly regarding the proposed dual carriageway upgrade of the A1 highway.

The 2025 State of the Nation Address announced plans to upgrade the 640-kilometre road from Ramatlabama to Ramokgwebana through a public-private partnership model.

Under the proposal, a private concessionaire would be responsible for design, financing, construction, operation and maintenance, while toll revenues would support the investment.

At the time, government indicated that a bankable feasibility study would be required before procurement of a private-sector partner could proceed.

The study was expected to begin in August 2025 and conclude by April 2026, with procurement targeted for September 2026.

However, the 2026 State of the Nation Address provided no update on the feasibility study or procurement process.

Instead, President Duma Boko announced P772.4 million in funding for urgent maintenance work on six sections of the A1 corridor.

 

Government Promises Tighter Project Selection

 

The 2027/28 Budget Strategy Paper signals a more disciplined approach to development expenditure.

Government says it will prioritise projects that are sufficiently prepared and capable of being completed within available fiscal resources.

The coming financial year will emphasise completion of ongoing high-impact projects before new projects are initiated.

The Ministry has specifically identified feasibility studies, detailed engineering designs and realistic cost estimates as core components of project readiness.

The proposed reforms also aim to align budget allocations with project preparedness, procurement timelines, implementation capacity and realistic expenditure schedules.

Government further says it will improve disclosure of delayed spending, review underperforming projects and, where necessary, rescope or discontinue projects that are no longer viable.

 

 

 

 

Tags: Development BudgetP36.6bnUnspent

Navigation

  • Home
  • News
  • Economy
  • E-Edition
  • Companies & Markets
  • In Business With
  • Lifestyle
    • Motoring
  • Sports
  • Subscribe

Recent News

  • P36.3bn Unspent as Development Budget Execution Falters
  • BoFiNet Eyes Regional Role for Digital Delta Data Centre
  • Botswana Records 18,101 Public Health Workers – Statistics Botswana Report
  • Collections by BK Proctor Set for Botswana’s Biggest Black Friday Sale
  • The Annual Staff Party Cannot Repair Eleven Months of Disrespect

Site

  • About
  • Advertise
  • Privacy Policy
  • Cookie Policy
  • Contact
  • Subscribe
  • E-edition

© 2021 The Business Weekly & Review. All Rights Reserved.

Welcome Back!

Login to your account below

Forgotten Password? Sign Up

Create New Account!

Fill the forms below to register

All fields are required. Log In

Retrieve your password

Please enter your username or email address to reset your password.

Log In
No Result
View All Result
  • Home
  • News
  • Economy
  • E-Edition
  • Companies & Markets
  • In Business With
  • Lifestyle
    • Motoring
  • Sports
  • Subscribe

© 2021 The Business Weekly & Review. All Rights Reserved.

This website uses cookies. By continuing to use this website you are giving consent to cookies being used. Visit our Privacy and Cookie Policy.
Not enough quota to unlock this post
Unlock left : 0
Are you sure want to cancel subscription?